Latest news from Heavy Lift & Project Forwarding International Magazine

Sarens and TII team up for Johan Sverdrup move

Sarens has transported a 12,200-tonne oil platform module measuring 110 m x 61 m x 26 m from factory to barge in Stord, Norway.

 

The Belgium-headquartered crane rental, heavy lifting and engineered transport specialist was tasked with jacking, weighing and load-out operations for the project.

The 200 m move to the barge involved the use of 432 axle lines of TII Group’s KAMAG K24 SPMTs, driven by 22 power pack units.

Sarens executed the project on behalf of client Kvaerner, which is building the housing platform in partnership with KBR. “Despite heavy rain and high winds, the operation was perfectly executed according to the project plan,” said project manager Tor Arne Naess.

TII Group noted that modules have reached weights of up to 17,200 tonnes. With no sign of this upward trend ending, the only manageable way to complete a load out of this scale is by using SPMTs.

In order to determine the weight of the module, Sarens operators used 32,500-tonne weighing cells. Next, they used four towers of Sarens’ CS5000 climbing system to jack the unit approximately 13 m above the barge deck so that the grillage could be installed.

It took 20 days to complete the rigging, due to the complex cribbing required to accommodate the surface of the underside of the module.

The module will be shipped to the Johan Sverdrup oilfield in the North Sea, off the coast of Norway, in early 2019. It will house over 200 workers and will include sleeping areas, kitchen, dining room, recreational areas, and utility control systems.

www.tii-group.com

www.sarens.com

Heavy Lift | News

Enerpac gantry in clinical lift thumbnail image

Enerpac gantry in clinical lift

November 22 - Industrial installation company Lifthing has used an Enerpac SBL500 gantry to install three proton therapy units at the University Hospitals Leuven (UZ Leuven) in Belgium.
Views: 1933
ALE expands jacking capacity in Europe thumbnail image

ALE expands jacking capacity in Europe

November 19 - ALE is expanding its fleet of jacking solutions with the delivery of a multi-point Mega Jack 300 system to its UK branch, bringing the total number of towers in the company’s global fleet to over 20.
Views: 2383
P&L skids to Kriel thumbnail image

P&L skids to Kriel

November 1 - South Africa’s P&L Machine Moving and Rigging has used an Enerpac SBL500 gantry system to position a refurbished 60-ton (54.3-tonne) skid-mounted electrical substation in preparation for onward transportation to Kriel.
Views: 2568

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.