Sarens raises the roof

Sarens has installed part of the Al Bayt stadium’s retractable roof in Qatar as part of the ongoing preparations for the 2022 FIFA World Cup.

To complete the tandem lift, Sarens utilised two crawler cranes – a 1,250-tonne capacity CC 6800 and a 750-tonne capacity LR 1750.

The main challenge of the project, completed on behalf of construction contractor Cimolai, was mobilising the equipment, said Sarens. Qatar’s World Cup Supreme Committee helped clear the crane through Customs.

While the LR 1750 was already on site, the CC 6800 had to be shipped from Germany, with parts of the crane configuration being shipped from Croatia.

www.sarens.com

Heavy Lift | News

ALE’s Kazakhstan road trip thumbnail image

ALE’s Kazakhstan road trip

July 16 - ALE has completed a 3,400 km overland delivery in Kazakhstan – the longest road haul the company has performed in the country.
Views: 258
ESTA joins EC best practise project thumbnail image

ESTA joins EC best practise project

July 16 - The European association of abnormal road transport and mobile cranes (ESTA) has been asked to support a European Commission study to “explore health, safety and environment (HSE) best practise in the wind power sector”.
Views: 317
LDA installs kite system  thumbnail image

LDA installs kite system 

July 16 - Louis Dreyfus Armateurs (LDA) has fitted its ro-ro vessel Ville de Bordeaux with an AirSeas kite system, as it looks to develop the use of wind propulsion technologies.
Views: 337

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.