Mammoet heats up in Texas

Mammoet has completed the demolition and replacement of five heater furnaces in Texas City, USA.

Due to limited available space in the refinery to lay down the boom and jib of Mammoet's CC8800 crawler cranes, the heavy lift specialist constructed the two cranes in mid-air.

The east CC8800 jib was installed while suspended in the air by two cranes, while the west CC8800 jib and the main boom were assembled in mid-air above inactive pipe racks.

Once completed, the two CC8800 cranes lifted more than 50 components over several months.

www.mammoet.com

Heavy Lift | News

Collett's super delivery to Willenhall thumbnail image

Collett's super delivery to Willenhall

December 14 - Collett & Sons has completed the delivery of a 170-tonne transformer using its girder bridge trailer from the port of Ellesmere to Willenhall substation in the UK.
Views: 149
Chipolbrok Atlantic’s adventure continues thumbnail image

Chipolbrok Atlantic’s adventure continues

December 13 - Chipolbrok Atlantic has completed its voyage from St Petersburg to India, loaded with 658 individual pieces with a combined weight of 4,110 tonnes.
Views: 375
Blue Water active on MV31 project thumbnail image

Blue Water active on MV31 project

December 13 - Having signed a master freight forwarding services agreement with MODEC Offshore Production Systems (MOPS) earlier this year, Blue Water Shipping has been providing logistics services on the FPSO Guanabara MV31 project.
Views: 267

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.