Heavy lift shipping company Volgo-Baltic Logistic, along with project forwarder Infotech Baltika, successfully delivered a vacuum column destined for Gazprom Neft's Omsk refinery, Russia.

The C-201 vacuum column, manufactured by Atommash in Volgodonsk, was delivered using a Volgo-Baltic Logistic ro-ro barge in late 2017. The column measured 52.3 m in length, 11 m in diameter, and weighed 518 tonnes.

Ro-ro barge 2034, towed by two tugboats, travelled 13,300 km from Volgodonsk via the Northern Sea Route, the Ob and Irtysh rivers, before making for Omsk.

In a second project, Volgo-Baltic Logistic was responsible for the delivery of various oversize components for Sibur's ZapSibNeftekhim petrochemical facility in Tobolsk, also in Russia.

Between July and September 2017, the company carried four 360-tonne boilers, 66 m-long washing and rectification columns weighing approximately 150 tonnes each, an 87 m butene column and an extruder for a polyethylene plant.

17,500 tonnes of equipment was transhipped at the port of Sabetta from seven oceangoing ships to 25 articulated tug barge (ATB) units, operated by Volgo-Baltic Logistic.

The Gulf of Ob only opened for navigation in July 2017 and both projects were executed in the shortest possible timeframe, said the company.

Volgo-Baltic Logistic is a subsidiary of North-Western Shipping Company (NWSC).

 

vblc.ru

infotech-baltika.com

www.sibur.ru

www.gazprom-neft.com

www.nwship.com

Heavy Lift | News

Collett's super delivery to Willenhall thumbnail image

Collett's super delivery to Willenhall

December 14 - Collett & Sons has completed the delivery of a 170-tonne transformer using its girder bridge trailer from the port of Ellesmere to Willenhall substation in the UK.
Views: 153
Chipolbrok Atlantic’s adventure continues thumbnail image

Chipolbrok Atlantic’s adventure continues

December 13 - Chipolbrok Atlantic has completed its voyage from St Petersburg to India, loaded with 658 individual pieces with a combined weight of 4,110 tonnes.
Views: 377
Blue Water active on MV31 project thumbnail image

Blue Water active on MV31 project

December 13 - Having signed a master freight forwarding services agreement with MODEC Offshore Production Systems (MOPS) earlier this year, Blue Water Shipping has been providing logistics services on the FPSO Guanabara MV31 project.
Views: 268

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.