ALE takes the road less travelled

ALE has transported two transformers, weighing 75 tonnes each, along a challenging 2,000 km route to the Al Farsha Substation in Saudi Arabia.

ALE has transported two transformers, weighing 75 tonnes each, along a challenging 2,000 km route to the Al Farsha Substation in Saudi Arabia.
After extensive engineering designs and route feasibility studies, ALE provided the client with a solution that would deliver the transformers to the project site while adhering to the project schedule and cost requirements.

The final route selected presented many different challenges, says ALE, including transporting the components across 13 cities and towns; climbing to an altitude of 2,500 m; descending 1,500 m downhill through mountain passes; negotiating 21 tunnels; performing civil works; and working in bad weather conditions.

According to ALE, as the route was so complex, it had never been attempted before. The UK-headquartered heavy lifting and engineered transport specialist said that previous attempts by other contractors were only able to deliver the transformers to Baish, on the western side of the mountain range.

The transformers were subsequently towed 700 km back to Jeddah. By approaching the mountain range from the northern side, ALE was able to deliver the components using conventional trailers and ballasted prime movers.



Maxwell Sampson, operations manager for ALE, said: “We sought a smart, feasible solution and acquired the necessary approvals, prepared the civil works and overcame the challenges of the route in a safe, timely and cost-effective manner.”



Within 11 days ALE had transported both transformers to the site. Installation of the transformers was completed five days after the transformers were delivered.

www.ale-heavylift.com

Heavy Lift | News

EMEA renewables to build on positive 2018 thumbnail image

EMEA renewables to build on positive 2018

February 21 - The latest data released by the Global Wind Energy Council (GWEC) shows that Africa and the Middle East installed 962 MW capacity of onshore wind power in 2018, an increase of more than 300 MW compared to 2017. 
Views: 360
DSV ups Panalpina bid as Agility enters the fray thumbnail image

DSV ups Panalpina bid as Agility enters the fray

February 15 - Panalpina’s board of directors confirmed that it has received a revised, non-binding proposal from DSV to acquire the company at a price of CHF180 (USD178.9) per share, all in cash.
Views: 1172
Höegh’s ro-ro solution to Dammam thumbnail image

Höegh’s ro-ro solution to Dammam

February 14 - Höegh Autoliners has delivered a 112-tonne transformer, manufactured by CG, from Antwerp to Dammam in Saudi Arabia, on behalf of Kintetsu World Express (KWE).
Views: 1064
Kaleido in Kuwait bridge delivery thumbnail image

Kaleido in Kuwait bridge delivery

February 11 - Spain-headquartered Kaleido Logistics has coordinated the delivery of several passenger boarding bridges destined for Kuwait International Airport.
Views: 1326

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.