Western picks Enerpac gantry for Humber project

Canadian heavy lift contractor, Western Mechanical, has used an Enerpac hydraulic gantry to replace bridge spans for the Humber River railroad bridge in Toronto, Canada.

Featuring a 24 m header beam, the gantry traversed the four-rail track bridge, allowing the 400-tonne bridge spans to be swapped out and replaced over the course of eight weekends.

Each span section weighed 400 tons (362.9 tonnes) and measured 100 ft (30.5 m) long, between 12-17 ft (3.7-5.2 m) wide and 9 ft (2.7 m) high.

Western Mechanical opted to use its Enerpac SBL1100 telescopic hydraulic gantry rather than a crane for the project. “The gantry is ideal for this type of heavy lift where you are handling a long, heavy structure. Using a crane would have been expensive, especially since all work on the bridge was carried out over eight weekends,” explained Rob Doucet, project manager for the heavy lift division of Western Mechanical.

The company installed its gantry track system parallel to the bridge and on either side. This approach relied on using a gantry header beam that was wider than the width of the bridge in order to avoid placing any excessive load on the partly deconstructed structure.

“We needed a header beam 24 m in length, which is far longer than we have used on past project lifts. Given the length of the header beam and load distribution, Enerpac recommended a wider header beam and modifications to the swivel interface where the header beam rested on the top of each gantry leg,” added Doucet.

Once the gantry was in place, Western Mechanical utilised the telescopic legs in order to lift the old spans clear of the bridge. The track system was then used to clear the structure, ready for the next span lift.

The Enerpac header beam and supporting side shift units moved the lifted span to awaiting railcars for onward transportation to the demolition yard.

www.westernmechanical.net

www.enerpac.com

Heavy Lift | News

Big Carl on show at Hinkley thumbnail image

Big Carl on show at Hinkley

September 13 - The giant Sarens SGC 250 ring crane is ready to start construction work at EDF’s Hinkley Point C nuclear power station.
Views: 429
Texas places Konecranes order thumbnail image

Texas places Konecranes order

September 11 - The port of Brownsville, USA, has placed an order with Konecranes for two Gottwald Model 6 mobile harbour cranes.
Views: 464
New brakes for Sleipnir cranes thumbnail image

New brakes for Sleipnir cranes

September 5 - Pintsch Bubenzer has installed a set of Twin Safe TS800 brakes on two 10,000-tonne capacity revolving cranes on board the semi-submersible vessel Sleipnir.
Views: 928

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.