Latest news from Heavy Lift & Project Forwarding International Magazine

Hill completes exchanger swap

Hill Crane & Rigging (HCR) has used a 500-ton (453.6-tonne) capacity heavy track HT500 hydraulic skidding system from Hydra-Slide to replace a stacked heat exchanger at a refinery in Carson, California.

HCR’s project scope included the removal of a 260,000-lbs (117.9-tonne) heat exchanger and the installation of a 279,000-lbs (126.6-tonne) replacement.

To execute this, HCR used the HT500 skidding system along with 100-ton (90.7-tonne) capacity modular support stands and a Hydra-Pac synchronous hydraulic power unit, all supplied by Hydra-Slide.

Darren Scruggs, senior account manger at HCR, said: “The slide system was one of the major components of the heavily engineered concept that we pitched to the refinery. Without removing overhead structure beams, a jack and slide solution was the only viable option. We worked closely with Hydra-Slide to put together a robust proposal and upon winning the contract, we placed orders for the necessary equipment, which remains in our fleet.”

HCR was also responsible for the transportation of the old exchanger to the manufacturer’s facilities, and the delivery of the new unit, which measured 27 ft 6 in (8.4 m) x 7 ft 6 in (2.3 m) x 15 ft (4.6 m).

For this part of the project, a 500-ton (453.6 tonne) capacity Enerpac gantry was used to load and offload the exchangers onto a dual lane trailer.

hillcrane.com

www.hydra-slide.com

www.enerpac.com

Heavy Lift | News

Chernobyl NSC wins project management accolade thumbnail image

Chernobyl NSC wins project management accolade

October 9 - As part of its 50th anniversary celebrations, the Project Management Institute has named Chernobyl’s New Safe Confinement (NSC) as one of the 50 most influential projects of the past 50 years.
Views: 2095
ALE reconfigures Nissan plant thumbnail image

ALE reconfigures Nissan plant

September 24 - UK-headquartered transport and rigging specialist ALE has completed a complex factory relocation project at the Nissan production plant in Pretoria, South Africa.
Views: 1720
ALE loads out in China thumbnail image

ALE loads out in China

September 6 - ALE has loaded out an 18,000-tonne topside at a yard in Zhuhai, China.
Views: 1691
RRS plans open house event thumbnail image

RRS plans open house event

August 14 - Rapid Response Solutions (RRS) will showcase the entire range of Hydra-Slide skidding equipment at its Portsmouth, UK facility on September 10, 2019.
Views: 1704

Heavy Lift Across The World