Mammoet skids out St. Jacques bridge

Mammoet has successfully completed the load-out and installation of the St. Jacques bridge in Montreal, Canada.

Mammoet, acting on behalf of the bridge developer Demathieu Bard – Aecon, used a new method of skidding to overcome site congestion and minimise disruption to traffic.

Mammoet’s skidding system usually consists of skid shoes placed in a skid track to move a load forward in a straight line. However, for this project it was not possible to use a skid track across the gap between the bearing points. The ministère des Transports de la Mobilité durable et de l’Électrification des transports (MTMDET) specified a new method to install the bridge across the two-lane interchange.

Instead, Mammoet designed a bespoke system consisting of separate skid shoes that could operate independently of a skid track. The remote-controlled shoes worked as separate units programmed in a synchronised, four-step sequence to push the bridge out across the span, without continuously moving the bridge forwards.

The skidding system was made up of Novarka skid shoes – the tailor-made 700-tonne capacity skid shoes used for the Chernobyl project in the Ukraine as reported by HLPFI here. (see page 25) 

In order minimise obstruction to the road network, the St. Jacques bridge was assembled alongside the highway, before being launched in two phases.

In the first phase, one half of the bridge was jacked up and placed on a system of eight skid shoes and temporary supports. The system pushed the structure forward from the east side of St. Jacques Street.

Vertical jacks lifted the bridge clear of the temporary supports and the skid shoes pushed it forward 0.6 m. The jacks then lowered the bridge back onto the supports as the skid shoes retracted 0.6 m to their starting point. This sequence was then repeated until the bridge was pushed out over a 45 m distance.

At this point the middle pier between the highways was able to support the structure at two points. The remaining half of the bridge was then constructed on the east side and attached to the first section.

In the second phase of the load-out, the complete bridge was pushed out a further 66 m until it completely spanned the highway below. This phase required 14 individual skid shoes operating on the eastern side of St. Jacques Street. Mammoet completed the job by jacking the bridge down 2 m onto its foundations.

Mammoet said that by using this innovative installation method, the disruption to traffic was minimised to only two weekends and a few nights.

www.mammoet.com

Heavy Lift | News

COLI opens Leer office thumbnail image

COLI opens Leer office

October 23 - The COLI Group has expanded its network with the opening of an office in Leer, Germany. 
Views: 134
Pallas set for LM-100J launch thumbnail image

Pallas set for LM-100J launch

October 23 - Lockheed Martin has announced that Pallas Aviation will be the first commercial freighter operator of its LM-100J, a variant of its C-130 Super Hercules aircraft.
Views: 118
Fesco supports Novatek project thumbnail image

Fesco supports Novatek project

October 23 - Fesco has handled the delivery of 1,742 tons (1,580.3 tonnes) of heavy-duty machinery to the construction site of Novatek’s Kola Shipyard in Belokamenka, in the Russian city of Murmansk.
Views: 106
ALL set to add 15 Liebherr cranes thumbnail image

ALL set to add 15 Liebherr cranes

October 23 - North American crane rental company, ALL Family of Companies, has acquired 15 all-terrain cranes from Liebherr, with the units scheduled for delivery throughout 2019.
Views: 159

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.