SAL bridges the gap

SAL Heavy Lift has transported 12 bridge sections from China to Norway in support Beitstadsundbrua bridge construction project in northern Trøndelag.

All 12 sections weighed 2,800 tonnes in total. The heaviest unit weighed 426 tonnes and measured 73.8 m x 9 m x 5.8 m; the longest unit measured 75 m x 5.9 m x 5.8 m and weighed 327 tonnes.

The components were loaded onto SAL Heavy Lift’s vessel Trina in Nantong for onward transportation to Malm, Norway.

Sune Thorleifsson, head of projects at SAL Heavy Lift, said it took 35 days to directly sail to Malm from Nantong in China. Despite the unique conditions in the port of Malm, with an only 20 m-wide jetty and 2 m tidal range, it took just six more days until the 20,668 cu m consignment was delivered to the client, according to Thorleifsson.

SAL Heavy Lift discharged the cargoes directly onto SPMTs in cooperation with its general agent at the port, Alex. Birger Grieg. Due to restrictions at the port, the SPMTs were located 25 m from from the vessel. The bridge sections were then transported to Fosdalen-Industrier’s assembly site.

The last unit was discharged in January 2019.

According to SAL Heavy Lift, the bridge sections will be installed later this year. Once complete, the bridge will measure 580 m in length and will connect the municipalities of Steinkjer and Malm, crossing the Beitstadfjorden.

sal-heavylift.com

www.alexgrieg.no

Heavy Lift | News

Multipurpose TOS introduced thumbnail image

Multipurpose TOS introduced

June 17 - CyberLogitec has introduced OPUS Terminal M, a multipurpose terminal operating system (TOS) that can coordinate containers, breakbulk, project, bulk and ro-ro cargoes.
Views: 226
Mohembo bridge parts move in Namibia thumbnail image

Mohembo bridge parts move in Namibia

June 17 - 10,720 tonnes of project cargo, destined for the Mohembo bridge project in Botswana, has moved through the port of Walvis Bay in Namibia.
Views: 250
Collett’s cold delivery thumbnail image

Collett’s cold delivery

June 17 - Collett & Sons has delivered three cold box sections from Eggborough in North Yorkshire to the West Midlands, UK.
Views: 279
GALA completes TAP scope thumbnail image

GALA completes TAP scope

June 17 - German Albanian Logistics Agency (GALA) has unloaded and stored 2,800 tons (2,540 tonnes) of sheet piles for the Trans Adriatic Pipeline (TAP).
Views: 237

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.