Al Faris doubles up

Al Faris has transported and lifted the 426-tonne precast girders for Dubai’s Route 2020 metro extension project.

Due to the confined space at the loading site, Al Faris opted for its SBL900 gantry system to load the components on its 19-axle Goldhofer THP/SL trailer, connected to a 680 horsepower heavy-duty prime mover.

The transportation to the project site and the lifting operations were subsequently completed at night, in order to avoid traffic on the roads and other obstacles, said Al Faris.

The precast girders were lifted and erected on the metro column using a 650-tonne capacity crawler crane, configured with a 42 m main boom.

According to Al Faris, the components were the heaviest precast girders to be installed as part of the Route 2020 project, which will extend the existing Dubai Metro Red Line to the Expo 2020 site.

In a separate project, Al Faris was responsible for the loading and transportation of a turret buoy from Dubai Industrial City to Jebel Ali Port.

Weighing 455 tonnes, and measuring 18.3 m in diameter and 16 m high, Al Faris claims the unit is the largest and heaviest turret buoy to be transported on road.

According to Al Faris the biggest challenge during transportation was manoeuvring the cargo, loaded on Goldhofer SPMTs, along narrow routes and sharp turns.

alfarisgroup.com

Heavy Lift | News

Myshak skids with Hydra-Slide thumbnail image

Myshak skids with Hydra-Slide

December 18 - Canada-based Myshak Crane & Rigging has utilised its Hydra-Slide hydraulic skidding equipment to replace a 514-tonne converter at a fertiliser production plant in Alberta.
Views: 278
Snowy delivery for Dan-Czech  thumbnail image

Snowy delivery for Dan-Czech 

December 18 - Dan-Czech Specialtransport has handled the delivery of two silos, each weighing 65 tonnes, from Benešov in the Czech Republic to Košice, Slovakia. 
Views: 189
Dhofar construction under way thumbnail image

Dhofar construction under way

December 18 - UK-headquartered ALE has started delivering and installing components for the Dhofar wind farm, located in Oman.
Views: 235
VIDEO: Dako's Colombian challenge thumbnail image

VIDEO: Dako's Colombian challenge

December 17 - Dako Worldwide Transport coordinated the movement of six heavy components, weighing around 100 tonnes each, as well as a further 10,000 freight tonnes from Europe to a 55 MW power plant in the Colombian mountains.
Views: 319

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.