ALE steels in Silao

ALE has lifted modules weighing up to 300 tonnes during the construction of a steel mill plant in Silao, Mexico.

Throughout January, ALE lifted several items at the project site, including roof panels and plant modules, using a 1,350-tonne capacity LR 11350 crawler crane.

The crane was configured with a P boom, which ALE said minimised congestion on site thanks to its small footprint. This in turn minimised disruption to the overall construction schedule and saved time and costs, according to ALE.

www.ale-heavylift.com

Heavy Lift | News

FROM THE MAGAZINE: Pumping up power thumbnail image

FROM THE MAGAZINE: Pumping up power

August 19 - As nations reduce their reliance on fossil-fuelled power generation, hydropower projects – in particular pumped storage schemes – will play a key role in supplementing wind and solar energy developments.
Views: 375
Jan De Nul secures Kriegers Flak work thumbnail image

Jan De Nul secures Kriegers Flak work

August 16 - Jan De Nul Group will transport and install 72 Siemens wind turbine generators – with a capacity of 8.4 MW each – for the Kriegers Flak offshore wind farm in Denmark.
Views: 689
Pretty in pink for TGP thumbnail image

Pretty in pink for TGP

August 16 - Trans Global Projects Group (TGP) has delivered 62 modules to a mining site near Newman, Australia.
Views: 598

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.