Oxbo on the double

Oxbo Mega Transport Solutions has coordinated the delivery and installation of ten engines and ten generators for a power plant project in southwest USA.

Weighing 158,400 lbs (71.8 tonnes), the generators measured 4.57 m x 3.96 m x 4.34 m; the engines weighed 642,840 lbs (291.6 tonnes) and measured 13.1 m x 4.1 m x 6.1 m.

Once the generators and 30 other components arrived at the project site by truck, Oxbo used platform trailers to move all of the items to the assembly area, where the units were moved into place using a gantry crane.

Using a gantry crane, Oxbo unloaded the engines from railcars and onto Goldhofer platform trailers for transport into a storage area.

In a few months, Oxbo will begin moving the engines on to their designated pads using a jack and slide system.

Meanwhile, Oxbo has transported two 355,110-lbs (161.1-tonne) transformers using a Goldhofer THP/CA dual lane transporter.

Each transformer measured 10.11 m x 3.71 m x 4.67 m. The entire configuration measured 118.8 m long and weighed 680.4 tonnes.

Upon arrival at the substation, crews used a jack and slide system to lower and set each transformer onto its pad.

 

www.oxboinc.com

Heavy Lift | News

Barnhart in steeple lift thumbnail image

Barnhart in steeple lift

April 23 - Barnhart Crane & Rigging has provided a 100-ton (90.7-tonne) lifting capacity crane to replace a 30 ft (9.1 m) church steeple in Nebraska, USA.
Views: 75
Tyne moves Bedford lifeboat thumbnail image

Tyne moves Bedford lifeboat

April 18 - After almost two years in covered storage, the historic Bedford lifeboat has been relocated from the port of Tyne to the North East Maritime Trust’s yard in the UK, ahead of a restoration project.
Views: 614
AAL calls in Felixstowe thumbnail image

AAL calls in Felixstowe

April 18 - AAL has made its inaugural call at the UK’s port of Felixstowe to deliver four rubber-tyred gantry cranes (RTG).
Views: 775
ALE moves crane in one piece thumbnail image

ALE moves crane in one piece

April 16 - ALE is utilising its fleet of SPMTs for the relocation of a Manitowoc 18000 crawler crane as part of the Loma Blanca wind farm project in Argentina.
Views: 843

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.