Latest news from Heavy Lift & Project Forwarding International Magazine

RRS skids for CTS

Rapid Response Solutions (RRS) has installed a 45-tonne transformer at the East Cowes power station on the Isle of Wight, UK on behalf of transport and logistics specialist CTS.

CTS contracted RRS to unload and skid the transformer, which was delivered from Italy, into position upon arrival at the project site. Manufactured by Tironi, the unit measured 6 m x 2.4 m x 4 m.

RRS selected its 270-tonne capacity HT300 hydraulic skidding system, manufactured by Hydra-Slide, for the project.

Paul Barber, managing director at RRS, said: “We used the HT300 because the ground conditions between the road and the final landing position 15 m away was not all concrete; some areas were just loose stone and were not load bearing. Uneven ground meant there was a 450 mm height difference from unloading position to landing spot.

“[Using the HT300] we were able to set the support stands out every 3 m to level the track in both directions. The HT300 is designed to work without the tracks being fully supported, allowing it to bridge gaps.”

A crane was considered for the project, but due to limited space onsite and the ground sloping difficulties, hydraulic skidding was the preferred option.

This was the second transformer RRS has installed at the project site in the past year.

www.rapidrs.co.uk

Heavy Lift | News

Big Carl arrives at Bristol Port thumbnail image

Big Carl arrives at Bristol Port

May 23 - Sarens’ SGC 250 crane is presently in storage at Bristol Port, UK ahead of its delivery to the Hinkley Point C nuclear power plant.
Views: 190
Superior bridge service with Imperial thumbnail image

Superior bridge service with Imperial

May 22 - Imperial Crane Services and Superior Construction have utilised a Liebherr LR1300 SX crawler crane to lift six concrete beams for the Chase Street bridge replacement project in California, USA.
Views: 383
EGL in transformer move thumbnail image

EGL in transformer move

May 21 - Egyptian Global Logistics (EGL) has unloaded and transported two transformers destined for a power station at Damietta Furniture City.
Views: 381
Marr towers ahead in Sydney Metro project thumbnail image

Marr towers ahead in Sydney Metro project

May 20 - At the end of 2018, Austrlian heavy lifting specialist Marr Contracting utilised two tower cranes to complete a key phase of the Sydney Metro infrastructure project.
Views: 546

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.