Seven up for ALE and Nordlink

ALE has transported and installed seven transformers, weighing approximately 225 tonnes each, for the Nordlink project in Tonstad, Norway.

ALE commenced operations in June last year, receiving the first two transformers at the port of Kvinesdal in Norway. The units were transported along a 70 km route through the Norwegian mountains using an AL100 girder frame and 26 axle lines of conventional trailers, as HLPFI reported here

The project took approximately five months to complete and, according to Paul Karlsen, regional manager - Scandinavia for ALE, required comprehensive planning and engineering to transport the transformers along the complex route. 

The Nordlink project, also referred to as the Green Cable project, will develop a 623 km-long high voltage direct current (HVDC) connection between Norway and Germany.

According to ALE, it will allow the exchange of renewable energy, especially hydroelectric power and wind power, between both countries.

A video of the project can be viewed here

 



www.ale-heavylift.com

Heavy Lift | News

Jan De Nul secures Kriegers Flak work thumbnail image

Jan De Nul secures Kriegers Flak work

August 16 - Jan De Nul Group will transport and install 72 Siemens wind turbine generators – with a capacity of 8.4 MW each – for the Kriegers Flak offshore wind farm in Denmark.
Views: 431
Pretty in pink for TGP thumbnail image

Pretty in pink for TGP

August 16 - Trans Global Projects Group (TGP) has delivered 62 modules to a mining site near Newman, Australia.
Views: 394
Trams roll to Mauritius thumbnail image

Trams roll to Mauritius

August 16 - Höegh Autoliners has transported 18 light rail vehicles (LRV) from Spain to Mauritius on its ro-ro vessel Höegh Antwerp.
Views: 398

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.