Latest news from Heavy Lift & Project Forwarding International Magazine

TGP supports Sangachal power plant project

UK-headquartered Trans Global Projects Group (TGP) has moved 22 engines from Trabzon Free Zone in Turkey for a 400 MW power station currently under construction in Sangachal, Azerbaijan.

The 17.7 MW engines, measuring 14 m x 4.5 m x 6.35 m and weighing around 295 tonnes each, had to be moved before the end of the navigable season of the Volga-Don canal system.

They were transported 2,745 km on three general cargo vessels from Trabzon to Baku, where TGP chartered the crane vessel Azerbaijan, which has a lifting capacity of 2,500 tonnes, for the discharge operations.

The engines completed their journey from Baku to Sangachal – 50 km south of the capital – on 16 and 20-axle self-propelled trailers. They were offloaded onto stillages at the site of the power plant using a 1,350-tonne capacity gantry system.

The power station is set to begin operating in 2020.

www.tglobal.com

Heavy Lift | News

Tyne moves Bedford lifeboat thumbnail image

Tyne moves Bedford lifeboat

April 18 - After almost two years in covered storage, the historic Bedford lifeboat has been relocated from the port of Tyne to the North East Maritime Trust’s yard in the UK, ahead of a restoration project.
Views: 312
AAL calls in Felixstowe thumbnail image

AAL calls in Felixstowe

April 18 - AAL has made its inaugural call at the UK’s port of Felixstowe to deliver four rubber-tyred gantry cranes (RTG).
Views: 418
ALE moves crane in one piece thumbnail image

ALE moves crane in one piece

April 16 - ALE is utilising its fleet of SPMTs for the relocation of a Manitowoc 18000 crawler crane as part of the Loma Blanca wind farm project in Argentina.
Views: 536

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.