Alistair completes mining moves 

Alistair Group has transported nearly 2,000 tons (1,814.4 tonnes) of steel structures from Durban, South Africa to a mining site in Kolwezi, Democratic Republic of the Congo.

In total, Alistair coordinated 62 truckloads to move the cargoes, seven of which were abnormal loads. 

The team had to liaise with the relevant authorities in order to obtain abnormal load permits, while mobile ‘road call’ vehicles were on hand to attend any breakdown to ensure the deliveries remained in accordance with the project schedule. 

Alistair’s project scope also included Customs clearance and the management of all route in transit clearances. 

“We provided our client with a single point of contact for all transport and logistics requirements and acted as their feet on the ground,” explained Alistair. 

www.alistairgroup.com 

Heavy Lift | News

Steel shipment for Alistair thumbnail image

Steel shipment for Alistair

April 2 - Alistair Group has transported steel structures from Durban, South Africa to Kolwezi in the Democratic Republic of the Congo.
Views: 503
GS Express moves in Malaysia thumbnail image

GS Express moves in Malaysia

March 31 - GS Express Logistics has transported three 88.8-ton (80.6-tonne) CO2 storage tanks from Westport, Port Klang to Kerteh, Malaysia.
Views: 636
Silos move to Slovakia thumbnail image

Silos move to Slovakia

March 30 - Bolk Transport and LS International Cargo have moved two silos from Schärding, Austria to Ružomberok, Slovakia.
Views: 686

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.