Latest news from Heavy Lift & Project Forwarding International Magazine

Collett transports transformer

Collett & Sons has moved a 170-tonne Hyundai transformer from Port Sutton Bridge in Lincolnshire to the Eaton Socon substation in St Neots, Cambridgeshire.


The transformer was 8.6 m long, 4.91 m wide and 4.75 m high. At Port Sutton Bridge, Collett carried out all port services including stevedoring, lift plans and crane hire. Collett was also responsible for discharging the cargo from the hold of the vessel on to its Scheuerle girder bridge.

The 78-mile (125.5-km) move required the removal of street furniture, contraflow manoeuvres and temporary parking restrictions to allow the 66 m long, 4.8 m high loaded combination to pass safely.

At the site, the cargo was delivered for installation via a pre-positioned trackway.

Collett completed jacking and skidding operations to manoeuvre the transformer onto the awaiting plinth.

www.collett.co.uk

Heavy Lift | News

Deliveries for South Flank begin thumbnail image

Deliveries for South Flank begin

December 12 - Mammoet has started transporting the first heavy components for the BHP South Flank iron ore mine, which is being developed in the Pilbara region of Western Australia.
Views: 655
Haslach adds LTM 1130-5.1 thumbnail image

Haslach adds LTM 1130-5.1

December 12 - German crane contractor Haslach has taken delivery of a new Liebherr LTM 1130-5.1.
Views: 339
CS Wind places Kalmar order  thumbnail image

CS Wind places Kalmar order 

December 6 - Kalmar will supply CS Wind Vietnam with two Super Gloria reachstackers, each with a lifting capacity of 100 tons (90.7 tonnes). 
Views: 980

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.