Miroslav Jakab, Fluor Fellow - logistics, shares the first in a series of articles detailing the intricacies, nuances and importance of EPC project logistics. The season kicks off with analysis of the environment that governs EPC projects and provides the foundation for subsequent articles that delve deeper into dealing with EPC project logistics.

The intention of this series is to contribute to increased mutual understanding among EPC logistics departments and logistics service providers. We encourage you to share your feedback with us, so we can incorporate observations into coming articles.

Introduction

“Logistics is defined as those activities that relate to receiving the right product or service in the right quantity, in the right quality, in the right place, at the right time, delivering to the right customer, and doing this at the right cost,” as stated by Shapiro, D. Roy., Heskett, L. James., 1985 in Logistics Strategy: Cases and Concepts.

This explanation appeals to Fluor and encompasses the soul and purpose of meaningful logistics, a specialty that requires strategy, planning, prioritisation, and the movement of resources.

When considering logistics management for the engineering, procurement and construction (EPC) industry – for which typical projects include those related to oil and gas, mining, renewable energy, petrochemicals and infrastructure – I want to stress that the specialty includes much more than ‘just’ physical movement of material and equipment from one location to another. I will attempt to describe its complexity and mutual interfaces in detail a little later, but first it is important to understand a typical EPC project life cycle.

Life cycle of an EPC project

In general, EPC projects can be divided into two main parts: front-end loading, and back-end loading.

The Front-end loading of a [facilities design and construction] project can be described as the process by which a company (and project team) translates its marketing and technological opportunities into capital projects. In other words, during the front-end loading phase, the questions of ‘why, what, when, how, where and who’ are answered.

The objective of the front-end loading phase is to achieve a detailed definition of a project’s scope and what is required needed to satisfy the business objectives for the capital investment.

By providing a detailed project definition that can be communicated and agreed upon by all project participants prior to authorization (prior to authorisation of the project start phase), the number of changes that could be required in later project stages are minimised. The project outcomes are therefore, theoretically, more predictable.

The FEL phase is defined as the period from when a business opportunity is identified and to the point at which a project capitalizing on the business opportunity is authorized.

Even though the detailed definition of front-end loading may differ among different stakeholders, it can be generally divided into three phases: FEL 1 (identify); FEL 2 (select); FEL 3 (define)

Back-end loading typically consists of two phases: EPC (execute), and start-up and operation (operate).

Table 1: Project Lifecycle Main Phases:

Typical Phases:FEL 1FEL 2FEL 3EPCStart up and Operation

Brief Description:

IDENTIFY

SELECT

DEFINE

EXECUTE

OPERATE

Content:

Concept Development

Conceptual Planning

Detailed Scope Definition

Engineering

Operation and Production

Feasibility Analysis

Conceptual Engineering

Preliminary Engineering

Procurement

Business Planning

Pre-FEED*

FEED*

Construction

With respect to EPC project logistics, the majority of planning and strategszing is performed/must be articulated during front-end loading phases. During this stage, the cargo envelopes in terms of maximum shipping dimensions and weights, feasibility of moving material and equipment from multiple locations etc. would be evaluated.

The cargo starts moving during the back-end loading – EPC phase. Successful logistics execution draws on the early preparation to perform to the baseline. To summarise:

– Front End Loading phase:

i) Plan - Define - Optimize

–  EPC phase (Back End Loading):

i) Deliver to baseline

The reasoning for and visualisation of the aforementioned stages is demonstrated by the ‘influence and expenditure curve for project life cycle’ as described in Pre-Project Planning Handbook, published by the Construction Industry Institute. It is illustrated in figure one with slight adjustments to reflect the project lifecycle phases described above:

Figure 1- The Influence and Expenditure Curve for Project Life Cycle

Source: Fluor

Figure 1: The influence and expenditure curve for the project life cycle

The graph clearly illustrates the importance of front-end loading phases and their impact on the overall schedule and costs for projects.

Nevertheless, there are multiple practical reasons that do not allow projects to embark upon a thorough planning during the front-end loading phase. Even though the precise scope should be initially defined, it will be continually changed during project development. It is important not only to have proper change procedures in place, and a flexible mindset and attitude for all stakeholders.

As per Fluor’s own experience, the best approach is the combination of both these approaches with added optimisation during execution:

- Proper and detailed planning including scope and contract definition during front-end loading.

- Building a highly capable and efficient project ecosystem (including all the key partners and suppliers) that is dedicated to making the project a success, through cooperation and collaboration.

- Optimising the execution phase to proactively address situations and mitigate potentially negative impacts, both on cost as well as on schedule

An EPC project’s cost and schedule benchmarks

Nevertheless, the impossibility of developing perfect plans has been well documented in the context of projects.

McKinsey & Company in 2017, based on analyzing 274 projects with budgets exceeding USD1 billion, published the cost and schedule overrun figures, as detailed in table two.

Table two: Overview of costs and schedule overrun for project exceeding USD1 billion.

INDUSTRYCOST OVERRUN1SCHEDULE OVERRUN2

O&G Downstream

53%

38%

Mining

53%

41%

Other Infrastructure

43%

63%

Transport

40%

63%

O&G Upstream

34%

41%

O&G Midstream

28%

69%

Real Estate

24%

85%

Average

37%

53%

1 Cost overrun = (actual cost – budgeted costs) / budgeted cost

2 Schedule overrun = delivery delay / budget duration

Further, McKinsey & Company, based on IHS Global Database, analyzed 137 projects and publicized the findings [10] with respect to project schedule delays in 2020:

Table 3: Overview of projects schedule delays

INDUSTRYDELAYS IN PROJECTS (% of average)NUMBER OF YEARS DELAYED (average)NUMBER OF PROJECTS

Mining

60%

2.2 years

11

Oil & Gas

68%

1.8 years

55

Power

67%

2.0 years

3

Real Estate

92%

2.0 years

12

Transport

69%

2.3 years

44

Other Infrastructure

108%

2.8 years

12

According to another consultant, KPMG, which published Climbing the Curve; 2015 Global Construction Project Owner’s Survey, only 25 percent of analysed projects came within 10 percent of their original deadlines. Just 31 percent of the projects came within 10 percent of their budget.

Even though there are many reasons for these results, from many available surveys and publicized literature, it can be concluded that material and equipment readiness and delivery have an impact on the project schedule and costs.

According to EA Silver, writing in the timing and sizing of procurement and logistics actions in large-scale projects: ‘‘The performance of large-scale projects depends to a major extent on the effectiveness of decision-making in the materials management area’.’

Many other researchers and specialists confirm this in their studies, among them being Mary Bajomo et al., writing in the International Journal of Production Economics, who stated: “The importance of managing material procurement and logistics towards the success of construction projects cannot be over-emphasised. This is especially true to EPC industry.”

EPC project logistics finds itself in a unique position, which can be described succinctly by ‘the lever effect’ (see image below), and that despite being a small proportion of the project cost, logistics can impact a large part of procurement and construction costs, as well as schedule overruns.

The lever effect in project logistics

Source: Fluor

The ‘lever effect’ in project logistics.

In the second part of this series of articles, I will discuss EPC project logistics in greater detail at various project stages, together with logistics service providers’ involvement in the process. We will articulate how logistics can play a major part in becoming a value-generating function and move away from being considered a cost.