Modulift supplies beams for jacket lifts

Lifting equipment manufacturer Modulift has supplied two large spreader beams to ST3 Offshore's terminal in Poland, which are being used to lift wind (turbine) jacket foundations.

The spreader beams - two 8 m-long MOD 400/600s - will form part of a rig that will be used to lift and position 20 jackets onto barges bound for Cuxhaven, Germany; the jackets will eventually be installed at the Borkum Riffgrund 2 offshore wind farm.

The two MOD 400/600s are being used in an inverted configuration above another Modulift beam, an 800/1000, which was hired from Schmidbauer. The beams combine with shackles and other rigging gear, including delta plates, to form the rig beneath the hooks of a rail-mounted, 117m-high, 1,400-tonne capacity gantry crane.

Each jacket foundation weighs 700 tonnes and measures 52 m high. Each barge can transport three jackets per voyage.

John Baker, sales and marketing director at Modulift, said that the top two 400/600 beams are used in an inverted configuration to utilise the four hoist hooks on the gantry crane. This allows the lower slings to come down to a single point on top of the lower 1,000-tonne capacity beam. Below that, two delta plates and a horizontal sling create the vertical angle for the bottom slings, which attach the rig to the top of each jacket.

"Modulift spreader beams are put into compression when loaded so another beam wouldn't have been suitable at the bottom of the rig between the delta plates because the forces applied are tensile rather than compressive. A wire rope grommet acted as a tie sling between the delta plates and created the vertical sling angle for the bottommost slings in the rig," Baker explained.

Modulift says that the first phase of the loadout is ongoing and the lifting rig will remain in Szczecin for the duration of the project.

The gantry crane lifts the second of three jacket foundations to be loaded onto the awaiting vessel.

 

www.modulift.com

www.schmidbauer-group.com

Heavy Lift | News

Myshak skids with Hydra-Slide thumbnail image

Myshak skids with Hydra-Slide

December 18 - Canada-based Myshak Crane & Rigging has utilised its Hydra-Slide hydraulic skidding equipment to replace a 514-tonne converter at a fertiliser production plant in Alberta.
Views: 205
Snowy delivery for Dan-Czech  thumbnail image

Snowy delivery for Dan-Czech 

December 18 - Dan-Czech Specialtransport has handled the delivery of two silos, each weighing 65 tonnes, from Benešov in the Czech Republic to Košice, Slovakia. 
Views: 146
Dhofar construction under way thumbnail image

Dhofar construction under way

December 18 - UK-headquartered ALE has started delivering and installing components for the Dhofar wind farm, located in Oman.
Views: 153
VIDEO: Dako's Colombian challenge thumbnail image

VIDEO: Dako's Colombian challenge

December 17 - Dako Worldwide Transport coordinated the movement of six heavy components, weighing around 100 tonnes each, as well as a further 10,000 freight tonnes from Europe to a 55 MW power plant in the Colombian mountains.
Views: 277

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.