Egytrans deploys gantry system for power plant project

Egytrans has transported and lifted a 245-ton (222.3-tonne) turbine and 290-ton (263.1-tonne) generator for a power plant construction project in western Cairo, Egypt.

Both units had to be lifted to a height of 16 m, said Egytrans. They were then skidded along a 50 m track to reach their foundations using a strand jack gantry system from Enerpac.

The turbine and generator had to be rotated 90 degrees before Egytrans could move the units to their final positions.

Earlier this year, the company relocated its Cairo head office to Down Town Katameya Mall. Egytrans’ new location can be found here.

egytrans.com

Heavy Lift | News

Challenges facing towage and offshore operators thumbnail image

Challenges facing towage and offshore operators

September 20 - Sandro Lipani, director chartering and operations for Malta-based Augustea Maritime Transportation, discusses some of the challenges of operating in the towage and offshore support sector.
Views: 439
Allseas wins decommissioning work thumbnail image

Allseas wins decommissioning work

September 20 - Allseas has been awarded a contract for the removal, transfer, load in and disposal of the Gyda platform in the Norwegian part of the North Sea.
Views: 326
Innovation overhauled thumbnail image

Innovation overhauled

September 20 - DEME’s offshore installation vessel Innovation has undergone a major refit at Damen’s Verolme shipyard in Rotterdam.
Views: 373
Sun shines with Chipolbrok thumbnail image

Sun shines with Chipolbrok

September 20 - Chipolbrok has delivered a range of heavy and oversized components using its vessel Chipolbrok Sun, including 56 wind turbine tower sections in Piteå, Sweden.
Views: 322

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.