Egytrans deploys gantry system for power plant project

Egytrans has transported and lifted a 245-ton (222.3-tonne) turbine and 290-ton (263.1-tonne) generator for a power plant construction project in western Cairo, Egypt.

Both units had to be lifted to a height of 16 m, said Egytrans. They were then skidded along a 50 m track to reach their foundations using a strand jack gantry system from Enerpac.

The turbine and generator had to be rotated 90 degrees before Egytrans could move the units to their final positions.

Earlier this year, the company relocated its Cairo head office to Down Town Katameya Mall. Egytrans’ new location can be found here.

egytrans.com

Heavy Lift | News

Rotterdam moves ahead with rail link thumbnail image

Rotterdam moves ahead with rail link

June 2 - A steel arch bridge has been installed across the Thomassentunnel and the A15 and N15 motorways in the Netherlands, forming a key link in the port of Rotterdam’s proposed Theemswegtracé railway line.
Views: 405
Martin Bencher skids in Sweden thumbnail image

Martin Bencher skids in Sweden

June 2 - Martin Bencher delivered a 186-tonne transformer from Helgum to Stor-Finnforsen, Sweden during May.
Views: 562
AML delivers to Russia thumbnail image

AML delivers to Russia

June 2 - Belgium-based freight forwarder AML has shipped a 955-tonne autoclave from Antwerp to De Kastri, Russia.
Views: 2110

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.