April 24 - Tradelossa has completed the transport of over-dimensional and overweight pieces for the Etileno XXI project in Coatzacoalcos, Veracruz.

Further to the news posted by HLPFI on March 27, 2013 regarding the movement of an 880-tonne splitter column for the project, the work has now been completed.

The project included the transportation of a 570-tonne bullet (pressure vessel); a 275-tonne boiler; a 395-tonne quench tower; a 215-tonne water tank; and the 880-tonne splitter column.

In total Tradelossa moved 29,446 tonnes of cargo during 1,004 trips for the Etileno XXI project.

Watch a video of the project here:

 

 

 