ALE takes the road less travelled

ALE has transported two transformers, weighing 75 tonnes each, along a challenging 2,000 km route to the Al Farsha Substation in Saudi Arabia.

ALE has transported two transformers, weighing 75 tonnes each, along a challenging 2,000 km route to the Al Farsha Substation in Saudi Arabia.
After extensive engineering designs and route feasibility studies, ALE provided the client with a solution that would deliver the transformers to the project site while adhering to the project schedule and cost requirements.

The final route selected presented many different challenges, says ALE, including transporting the components across 13 cities and towns; climbing to an altitude of 2,500 m; descending 1,500 m downhill through mountain passes; negotiating 21 tunnels; performing civil works; and working in bad weather conditions.

According to ALE, as the route was so complex, it had never been attempted before. The UK-headquartered heavy lifting and engineered transport specialist said that previous attempts by other contractors were only able to deliver the transformers to Baish, on the western side of the mountain range.

The transformers were subsequently towed 700 km back to Jeddah. By approaching the mountain range from the northern side, ALE was able to deliver the components using conventional trailers and ballasted prime movers.



Maxwell Sampson, operations manager for ALE, said: “We sought a smart, feasible solution and acquired the necessary approvals, prepared the civil works and overcame the challenges of the route in a safe, timely and cost-effective manner.”



Within 11 days ALE had transported both transformers to the site. Installation of the transformers was completed five days after the transformers were delivered.

www.ale-heavylift.com

Heavy Lift | News

Kässbohrer on display at bauma thumbnail image

Kässbohrer on display at bauma

March 22 - Kässbohrer is showcasing its range of lowbed trailers at the bauma 2019 exhibition, which takes place between April 8-14 in Munich.
Views: 405
Elbe Project Cargo Line launched thumbnail image

Elbe Project Cargo Line launched

March 22 - Sächsische Binnenhäfen Oberelbe, in cooperation with Deutsche Binnenreederei, launched the Elbe Project Cargo Line (EPCL) – a liner service for oversize and heavy project cargoes.
Views: 655
Mammoet moves for Mitsubishi thumbnail image

Mammoet moves for Mitsubishi

March 22 - Mammoet has delivered and installed 120 pressure vessels and modules for the construction of the Caribbean Gas Chemical Limited (CGCL) methanol and dimethyl ether (DME) plant in La Brea, Trinidad and Tobago.
Views: 862

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.