Bolloré completes Muara Laboh work

Bolloré Logistics has coordinated 50 shipments for Sumitomo Corporation’s Muara Laboh geothermal power plant project in West Sumatra, Indonesia.

In total, Bolloré handled the delivery of 15,000 freight tons of cargo, including a 95-ton (86.2-tonne) generator stator and a 65-ton (59-tonne) turbine rotor. Critical equipment was shipped from the port of Yokohama, Japan to Padang, Indonesia. Other origin ports were located in China, South Korea, Malaysia, Europe and the USA.

Located 150 km away from Padang port, Bolloré overcame steep, winding roads to access the project site; the company completed its first road surveys in 2016, prior to the project’s start date in 2018.

For the generator stator and turbine rotor transport operations, Bolloré mobilised three prime movers.

Bolloré completed its project scope in March 2019.

www.bollore-logistics.com

Heavy Lift | News

AET places Kalmar order thumbnail image

AET places Kalmar order

June 14 - Antwerp Euroterminal (AET) has placed an order for six Kalmar forklifts, including a fully electric model. 
Views: 417
Multipurpose charter rates remain stable thumbnail image

Multipurpose charter rates remain stable

June 14 - Time charter rates in the multipurpose shipping sector have remained stable over the last month, according to the latest data from shipbroker Toepfer Transport.
Views: 516
Buss launches JV with Idea thumbnail image

Buss launches JV with Idea

June 14 - Hamburg-based Buss Offshore Solutions and French logistics provider Idea established a joint venture that will serve the offshore market in France.
Views: 487

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.