Kuehne + Nagel on the transformer trail

Kuehne + Nagel (K+N) is coordinating the delivery of 11 transformers for various National Grid substations around the UK.

All transformers are being shipped from Busan, South Korea and delivered to 11 difference project sites. Since the beginning of the year, K+N has completed four of these shipments.

For the Bishops Wood substation, K+N was responsible for the delivery of a 240 MVA weighing 178 tonnes. Ten containers were also delivered to the site.

Similar shipments have been delivered to National Grid’s Cellarhead, Tilbury and Eaton Socon sites.

K+N’s scope of work includes shipping, transportation to site and installation on behalf of its client Posco International.

In addition, K+N has been awarded another contract for the delivery of two Hyosung transformers in 2020. The forwarder also has a pending contract for the delivery of another 40 transformers over the next three years.

kuehne-nagel.com

Heavy Lift | News

Collett delivers footbridge thumbnail image

Collett delivers footbridge

July 19 - Collett & Sons has delivered six over-dimensional bridge components to Worcester in the UK.
Views: 398
Sims Crane appoints Lester thumbnail image

Sims Crane appoints Lester

July 19 - Florida’s Sims Crane & Equipment has named Jared Lester as its business development manager. 
Views: 500
ITI and FHS to open Florida training centre thumbnail image

ITI and FHS to open Florida training centre

July 19 - Florida Handling Systems (FHS), a Mazzella Company, and Industrial Training International (ITI) have confirmed that they will develop a training centre in Bartow, Florida.
Views: 500

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.