Mammoet delivers Edmonton rail spans

Mammoet has installed two concrete bridge spans as part of the 13 km Valley Line LRT light rail guideway project in Edmonton, Alberta.

On behalf of TransEd Partners - composed of Bechtel, EllisDon, Bombardier and Fengate Capital Management - Mammoet used its accelerated bridge construction (ABC) method to install the spans over the course of two nights. 

“The ABC method allowed the TransEd joint venture to cast the concrete guideway spans next to the installation site in a controlled location, at a lower elevation,” said Mammoet.

The spans were then moved and put in place using the JS500 jacking system on top of SPMTs. According to TransEd, each span weighed approximately 600 tons (544.3 tonnes) and measured more than 32 m in length. 

The two installations each took place overnight to minimise disruption, with the motorway re-opening at 6am.

Mammoet is to continue installing the rest of the bridge guideway later this year.

www.mammoet.com

transedlrt.ca

Heavy Lift | News

FROM THE MAGAZINE: Pumping up power thumbnail image

FROM THE MAGAZINE: Pumping up power

August 19 - As nations reduce their reliance on fossil-fuelled power generation, hydropower projects – in particular pumped storage schemes – will play a key role in supplementing wind and solar energy developments.
Views: 346
Jan De Nul secures Kriegers Flak work thumbnail image

Jan De Nul secures Kriegers Flak work

August 16 - Jan De Nul Group will transport and install 72 Siemens wind turbine generators – with a capacity of 8.4 MW each – for the Kriegers Flak offshore wind farm in Denmark.
Views: 676
Pretty in pink for TGP thumbnail image

Pretty in pink for TGP

August 16 - Trans Global Projects Group (TGP) has delivered 62 modules to a mining site near Newman, Australia.
Views: 591

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.