Mammoet skids out St. Jacques bridge

Mammoet has successfully completed the load-out and installation of the St. Jacques bridge in Montreal, Canada.

Mammoet, acting on behalf of the bridge developer Demathieu Bard – Aecon, used a new method of skidding to overcome site congestion and minimise disruption to traffic.

Mammoet’s skidding system usually consists of skid shoes placed in a skid track to move a load forward in a straight line. However, for this project it was not possible to use a skid track across the gap between the bearing points. The ministère des Transports de la Mobilité durable et de l’Électrification des transports (MTMDET) specified a new method to install the bridge across the two-lane interchange.

Instead, Mammoet designed a bespoke system consisting of separate skid shoes that could operate independently of a skid track. The remote-controlled shoes worked as separate units programmed in a synchronised, four-step sequence to push the bridge out across the span, without continuously moving the bridge forwards.

The skidding system was made up of Novarka skid shoes – the tailor-made 700-tonne capacity skid shoes used for the Chernobyl project in the Ukraine as reported by HLPFI here. (see page 25) 

In order minimise obstruction to the road network, the St. Jacques bridge was assembled alongside the highway, before being launched in two phases.

In the first phase, one half of the bridge was jacked up and placed on a system of eight skid shoes and temporary supports. The system pushed the structure forward from the east side of St. Jacques Street.

Vertical jacks lifted the bridge clear of the temporary supports and the skid shoes pushed it forward 0.6 m. The jacks then lowered the bridge back onto the supports as the skid shoes retracted 0.6 m to their starting point. This sequence was then repeated until the bridge was pushed out over a 45 m distance.

At this point the middle pier between the highways was able to support the structure at two points. The remaining half of the bridge was then constructed on the east side and attached to the first section.

In the second phase of the load-out, the complete bridge was pushed out a further 66 m until it completely spanned the highway below. This phase required 14 individual skid shoes operating on the eastern side of St. Jacques Street. Mammoet completed the job by jacking the bridge down 2 m onto its foundations.

Mammoet said that by using this innovative installation method, the disruption to traffic was minimised to only two weekends and a few nights.

www.mammoet.com

Heavy Lift | News

Houston, we have a problem: Wood wasps thumbnail image

Houston, we have a problem: Wood wasps

October 22 - C Logistics Solutions (CLS) has supported the delivery of equipment to a chemical plant in Houston after the US authorities found the packing to be contaminated with wood wasps and ordered the cargoes to be reloaded and the vessel ejected from the port.
Views: 268
NHH handles dump truck delivery thumbnail image

NHH handles dump truck delivery

October 22 - Australia’s National Heavy Haulage (NHH), part of the National Group, has delivered five Ultra-Class Liebherr T 282 C dump trucks to BHP Billiton’s Peak Downs mining site in Queensland.
Views: 329
PLA members team up thumbnail image

PLA members team up

October 19 - Alexander Global Logistics, in cooperation with C.H. Robinson and ILG Logistics, has transported 24 mining dump trucks, each weighing 300 tons (272 tonnes), from various locations in Europe and the Americas.
Views: 557
Jumbo sails from Taiwan to Texas thumbnail image

Jumbo sails from Taiwan to Texas

October 19 - Jumbo has transported 16 petrochemical columns, as well as accompanying general cargo, from Mailiao in Taiwan to Texas, USA on behalf of Pacific Ocean Group.
Views: 620

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.