DEME Offshore has completed the installation of 58 Siemens Gamesa 8.4 MW turbines at the SeaMade offshore wind farm, located 45 km off the Belgian coast.

Construction of the wind farm began in September 2019. DEME oversaw the engineering, procurement, construction, and installation (EPCI) of the foundations, inter-array and export cables, in addition to the installation of two offshore substations.

DEME Offshore installed the first turbine at the SeaMade offshore wind farm in June 2020, as HLPFI reported here. It deployed its vessel Apollo for the works – the ship’s first turbine installation project.