February 9 - Van der Vlist coordinated the delivery of five out-of-gauge piling rigs used in a Volkswagen factory construction project from northeastern Germany to Poznan in Poland.

Each rig tipped the scales are around 80 tonnes and measured 20 m x 3.5 m x 3.5 m, and were moved to the project site using modular trailers. The machines, which were used by construction contractor Pfahl König to install 3,500 concrete piles, were redelivered to Germany upon completion of the works.

Van der Vlist also arranged the delivery of an array of additional parts and tools to the jobsite in 25 separate deliveries.

 

 

www.vandervlist.com