October 17 - BNSF Logistics, through its office in Banning, has handled the transport of three transformers, each weighing 315 tonnes from the port of Baltimore to Newark.

The transformers were transported by rail to the substation, offloaded, set on turntables, rotated 90 degrees and then placed on to their foundations.
 
The work on site was completed within one week.
 
BNSF Logistics is the US member for the Worldwide Project Consortium (WWPC).

 

www.bnsflogistics.com  
 
www.wwpc.eu.com