Daco brings the blades

December 2 - Heavy transportation specialist Daco Heavy Lift de Centroamerica has recently completed wind farm projects in Panamá, Costa Rica, Nicaragua, Honduras, and in its domestic market of Guatemala.

 

According to Daco Heavy Lift, the shipment of wind turbine equipment to a project site in Viento Blanco, Guatemala, was particularly challenging.
The park is constructed on the slopes of the active volcano Pacaya, which is situated between Guatemala City and the Pacific coast, close to the town of Palin.
Seven wind turbines had to be transported to the project site, with blades measuring 55 m long. The turbines were moved from Port Puerto Quetzal to Palin along a well-developed stretch of highway.
A 10 km long mountain road, with steep gradients and narrow curves, had to be negotiated to reach the final project site in the village of San Vicente Pacaya. Daco Heavy Lift was unable to reach the site using conventional extendible trailers, and the reconstruction of road infrastructure was prohibitively expensive.
Daco Heavy Lift utilised a Goldhofer blade lifter to help traverse the mountain pass. The company claims to be the first in the region to operate a hydraulic blade lifter.
In Palin, each blade was reloaded onto the Goldhofer trailer before being hauled to the final San Vicente Pacaya site.
Since many wind power generating plants in Central America are situated in mountainous areas, Daco Heavy Lift is convinced that there will be more opportunities to use this sophisticated equipment for future projects.
www.dacoheavylift.com

According to Daco Heavy Lift, the shipment of wind turbine equipment to a project site in Viento Blanco, Guatemala, was particularly challenging.

The park is constructed on the slopes of the active volcano Pacaya, which is situated between Guatemala City and the Pacific coast, close to the town of Palin.

Seven wind turbines had to be transported to the project site, with blades measuring 55 m long. The turbines were moved from Port Puerto Quetzal to Palin along a well-developed stretch of highway.

A 10 km long mountain road, with steep gradients and narrow curves, had to be negotiated to reach the final project site in the village of San Vicente Pacaya. Daco Heavy Lift was unable to reach the site using conventional extendible trailers, and the reconstruction of road infrastructure was prohibitively expensive.

Daco Heavy Lift utilised a Goldhofer blade lifter to help traverse the mountain pass. The company claims to be the first in the region to operate a hydraulic blade lifter.

In Palin, each blade was reloaded onto the Goldhofer trailer before being hauled to the final San Vicente Pacaya site.Since many wind power generating plants in Central America are situated in mountainous areas, Daco Heavy Lift is convinced that there will be more opportunities to use this sophisticated equipment for future projects.


www.dacoheavylift.com

Heavy Lift | News

Fesco and RZD team up to link Europe and Asia thumbnail image

Fesco and RZD team up to link Europe and Asia

May 24 - Fesco Transportation Group and Russian Railways Logistics (RZD Logistics) are launching a Trans-Siberian multimodal service to expedite the delivery of goods from Japan to Europe via Russia.
Views: 371
POSH to launch maritime training centre in Taiwan thumbnail image

POSH to launch maritime training centre in Taiwan

May 24 - POSH Kerry Renewables – a joint venture of PACC Offshore Services Holding (POSH) and Kerry TJ Logistics – has signed a memorandum of understanding (MoU) to develop Taiwan’s first specialised maritime training centre. 
Views: 302
PPG restructures training course thumbnail image

PPG restructures training course

May 24 - The Project Professionals Group (PPG) has restructured its project cargo forwarding training course into a one-day format.
Views: 316

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.