Big Carl on show at Hinkley

The giant Sarens SGC 250 ring crane is ready to start construction work at EDF’s Hinkley Point C nuclear power station.

Named Big Carl, the SGC 250 will play in a key role in constructing the nuclear power plant. Running along 6 km of rail track, the crane will lift 700 pieces – the largest items weighing 1,600 tonnes.

In its tallest configuration, the crane stands 250 m tall. It is powered by 12 engines and supported by 52 counterweight containers weighing 100 tonnes each.

The crane will complete the civil works on behalf of BYLOR, a joint venture between Laing O’Rourke and Bouygues.

www.edfenergy.com

www.sarens.com

Heavy Lift | News

Höegh boosts services to Australia thumbnail image

Höegh boosts services to Australia

September 23 - Höegh Autoliners will increase the frequency of its services from Europe to Australia to five sailings per month.
Views: 38
DYT places newbuild order thumbnail image

DYT places newbuild order

September 23 - DYT Yacht Transport has confirmed that it placed an order for a newbuild yacht transportation vessel.
Views: 36
Focus launch set for 2020 thumbnail image

Focus launch set for 2020

September 23 - Mammoet has started construction of its Focus crane – a heavy lifting solution for use in confined spaces such as plants and inner cities.
Views: 53
Challenges facing towage and offshore operators thumbnail image

Challenges facing towage and offshore operators

September 20 - Sandro Lipani, director chartering and operations for Malta-based Augustea Maritime Transportation, discusses some of the challenges of operating in the towage and offshore support sector.
Views: 515

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.