Latest news from Heavy Lift & Project Forwarding International Magazine

Collett transports transformer

Collett & Sons has moved a 170-tonne Hyundai transformer from Port Sutton Bridge in Lincolnshire to the Eaton Socon substation in St Neots, Cambridgeshire.


The transformer was 8.6 m long, 4.91 m wide and 4.75 m high. At Port Sutton Bridge, Collett carried out all port services including stevedoring, lift plans and crane hire. Collett was also responsible for discharging the cargo from the hold of the vessel on to its Scheuerle girder bridge.

The 78-mile (125.5-km) move required the removal of street furniture, contraflow manoeuvres and temporary parking restrictions to allow the 66 m long, 4.8 m high loaded combination to pass safely.

At the site, the cargo was delivered for installation via a pre-positioned trackway.

Collett completed jacking and skidding operations to manoeuvre the transformer onto the awaiting plinth.

www.collett.co.uk

Heavy Lift | News

Liebherr delivers a first in the USA thumbnail image

Liebherr delivers a first in the USA

February 19 - North Carolina Ports (NCP) has added a Liebherr LPS 420 rail-mounted gantry harbour crane at its terminal at the port of Morehead City.
Views: 117
Airfreight industry responds to coronavirus outbreak thumbnail image

Airfreight industry responds to coronavirus outbreak

February 19 - Russia’s Volga-Dnepr Group has operated sterilised charter flights to China to deliver masks, sanitiser gels, pharmaceuticals and medical equipment in response to the coronavirus outbreak.
Views: 122

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.