ALE deploys Mega Jack 300 in Kuwait

ALE has utilised its Mega Jack 300 to lift pipe rack modules of varying weights and sizes for the Al Zour Refinery Project EPC 2 and 3 in Kuwait. 

As part of the project, ALE is receiving pre-assembled pipe rack modules from barges at the project’s construction dock. The modules are subsequently transported 4 km on SPMTs to a staging area. 

Once at the staging area, the modules are lifted to various heights using the Mega Jack 300, which features 300-tonne capacity towers. 

A total of 188 modules will be delivered to the site, with some components measuring up to 40 m in length and weighing up to 2,100 tonnes. 

According to ALE, the components of the Mega Jack 300 system are both compact and easy to handle on site, meaning that re-configurations are made in as little time as possible. In addition, during the development phase, ALE was able to reduce the jacking time for the operations to approximately one or two hours. 

www.ale-heavylift.com

Heavy Lift | News

Tyne moves Bedford lifeboat thumbnail image

Tyne moves Bedford lifeboat

April 18 - After almost two years in covered storage, the historic Bedford lifeboat has been relocated from the port of Tyne to the North East Maritime Trust’s yard in the UK, ahead of a restoration project.
Views: 306
AAL calls in Felixstowe thumbnail image

AAL calls in Felixstowe

April 18 - AAL has made its inaugural call at the UK’s port of Felixstowe to deliver four rubber-tyred gantry cranes (RTG).
Views: 411
ALE moves crane in one piece thumbnail image

ALE moves crane in one piece

April 16 - ALE is utilising its fleet of SPMTs for the relocation of a Manitowoc 18000 crawler crane as part of the Loma Blanca wind farm project in Argentina.
Views: 529

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.