DEME Offshore has installed 47 out of the 94 foundations for Ørsted’s Borssele 1 & 2 offshore wind farm off the coast of the Netherlands.

Construction works began in January 2020 using the installation vessel Innovation. Despite significant downtime in February due to weather conditions, the installation of the foundations is on schedule for completion in early June, said DEME.