Turkish heavy lift and transport engineering company Hareket has been keeping busy working on the installation, dismantling and transport of heavy and oversized components. 

Hareket keeping busy with projects 1

Source: Hareket

Hareket installing one of four stack modules.

The first project involved the installation of four stack modules, which weighed more than 100 tonnes each. A Tadano AC500-8 crane, which has a lifting capacity of 500 tonnes, was used to install the stack. The total stack will reach a height of 82 m.

Hareket keeping busy with projects 2

Source: Hareket

One of the steel bridges which Hareket dismantled.

Meanwhile, Hareket has also been on hand to dismantle two steel bridges, each measuring 62 m x 6 m x 9 m, and weighing 250 tonnes respectively. The company opted for a tandem lift, including a 750-tonne capacity mobile crane and a 600-tonne capacity crawler crane to dismantle the components, which were then transported within the site using a 20-axle modular trailer configuration.

Last month, HLPFI reported that Hareket had invested in two state-of-the-art barges and signed an order agreement for 88 cranes from manufacturer Sany.