TGP supports Sangachal power plant project

UK-headquartered Trans Global Projects Group (TGP) has moved 22 engines from Trabzon Free Zone in Turkey for a 400 MW power station currently under construction in Sangachal, Azerbaijan.

The 17.7 MW engines, measuring 14 m x 4.5 m x 6.35 m and weighing around 295 tonnes each, had to be moved before the end of the navigable season of the Volga-Don canal system.

They were transported 2,745 km on three general cargo vessels from Trabzon to Baku, where TGP chartered the crane vessel Azerbaijan, which has a lifting capacity of 2,500 tonnes, for the discharge operations.

The engines completed their journey from Baku to Sangachal – 50 km south of the capital – on 16 and 20-axle self-propelled trailers. They were offloaded onto stillages at the site of the power plant using a 1,350-tonne capacity gantry system.

The power station is set to begin operating in 2020.

www.tglobal.com

Heavy Lift | News

Jan De Nul secures Kriegers Flak work thumbnail image

Jan De Nul secures Kriegers Flak work

August 16 - Jan De Nul Group will transport and install 72 Siemens wind turbine generators – with a capacity of 8.4 MW each – for the Kriegers Flak offshore wind farm in Denmark.
Views: 385
Pretty in pink for TGP thumbnail image

Pretty in pink for TGP

August 16 - Trans Global Projects Group (TGP) has delivered 62 modules to a mining site near Newman, Australia.
Views: 354
Trams roll to Mauritius thumbnail image

Trams roll to Mauritius

August 16 - Höegh Autoliners has transported 18 light rail vehicles (LRV) from Spain to Mauritius on its ro-ro vessel Höegh Antwerp.
Views: 347

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.