ALE pulls Cadiz jacket

October 5 - Heavy transport and installation specialist ALE has completed the load-out of a 22,400-tonne jacket for the Mariner Project in Cadiz, Spain.

The barge S44 was mobilised to complete the project. The barge was first grounded, which required the installation of an external ballast system. The jacket was then skidded on board using four pulling units, two of which had a 900-tonne capacity and a pair of 500-tonne capacity units. The jacket was moved a distance of 197 m.

The ballast system comprised of submersible pumps that were installed over the side of the barge, alongside vertical tubes to remove or add ballast water without interfering with the pulling manoeuvre.

ALE completed the load out over the course of six hours, pulling at an average speed of 16 m per hour.

 


www.ale-heavylift.com

Heavy Lift | News

Jan De Nul secures Kriegers Flak work thumbnail image

Jan De Nul secures Kriegers Flak work

August 16 - Jan De Nul Group will transport and install 72 Siemens wind turbine generators – with a capacity of 8.4 MW each – for the Kriegers Flak offshore wind farm in Denmark.
Views: 386
Pretty in pink for TGP thumbnail image

Pretty in pink for TGP

August 16 - Trans Global Projects Group (TGP) has delivered 62 modules to a mining site near Newman, Australia.
Views: 355
Trams roll to Mauritius thumbnail image

Trams roll to Mauritius

August 16 - Höegh Autoliners has transported 18 light rail vehicles (LRV) from Spain to Mauritius on its ro-ro vessel Höegh Antwerp.
Views: 349

Heavy Lift Across The World

Discover heavy lift and project logistics industry news from around the world by region.